Study Guides and Actual Real Exam Questions For Oracle OCP, MCSE, MCSA, CCNA, CompTIA


Advertise

Submit Braindumps

Forum

Tell A Friend

    Contact Us

 Home

 Search

Latest Brain Dumps

 BrainDump List

 Certifications Dumps

 Microsoft

 CompTIA

 Oracle

  Cisco
  CIW
  Novell
  Linux
  Sun
  Certs Notes
  How-Tos & Practices 
  Free Online Demos
  Free Online Quizzes
  Free Study Guides
  Free Online Sims
  Material Submission
  Test Vouchers
  Users Submissions
  Site Links
  Submit Site

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Online Training Demos and Learning Tutorials for Windows XP, 2000, 2003.

 

 

 

 





Braindumps for "000-253" Exam

trust me !!!!!

 trust me !!!!! 
visit ITCErtkeys
it is great site
thanks


Google
 
Web www.certsbraindumps.com


Braindumps: Dumps for PMI-001 Exam Brain Dump

Study Guides and Actual Real Exam Questions For Oracle OCP, MCSE, MCSA, CCNA, CompTIA


Advertise

Submit Braindumps

Forum

Tell A Friend

    Contact Us





Braindumps for "PMI-001" Exam

Project Management Professional Practice Test

 Question 1.
The inputs of the Performance Reporting process include all of the following except for which one?

A. Performance reviews
B. Work performance information
C. Forecasted completion
D. Performance measurements

Answer: A

Explanation:
Performance reviews are not an input of the Performance Reporting process. The remaining inputs of this process are quality control measurements, project management plan, approved change requests, and deliverables.

Question 2.
You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail store for the option of opening two new stores in a foreign country. You know, but have not yet informed your company, that you are going to go to work for the competitor, which happens to be bidding for this same opportunity. 

What is the most appropriate response?

A. You decide to participate in the initial meetings with the foreign business partners because any 
    information you gain now will help you when you make the move to the new company.
B. You inform the foreign business partners that you're going to be working with a new company 
    and that you know the deal they'll receive from the competing company is better than the one 
    this company is proposing.
C. You decline to participate in the initial meetings with the foreign business partners because of 
    a conflict of interest.
D. You've not yet received an official offer from the competing company for your new job 
    opportunity, so you choose to participate in the initial meetings with the foreign business 
    partners.

Answer: C

Explanation:
The most appropriate response is to decline to participate because of a conflict of interest.

Question 3.
The most effective team motivator is:

A. understanding the importance of the project
B. the satisfaction of meeting a challenge
C. All of the other alternatives apply.
D. the visibility of the team's contribution
E. the individual's professional challenge

Answer: D

Question 4.
Complete final contract performance reporting and verify product is done in _______ .

A. Conduct Procurements
B. Close Procurements
C. Plan Procurements
D. Administer Procurements

Answer: B

Explanation:
Complete final contract performance reporting and verify product is done in Close Procurements.

Question 5.
Continually measuring and monitoring the actual cost versus the budget is done to _____.

A. None of the other alternatives apply.
B. analyze the reasons for variances
C. establish the variances
D. identify the problems
E. All of the other alternatives apply.

Answer: E

Question 6.
You are a project manager for Giraffe Enterprises. You've recently taken over for a project manager who lied about his PMI certification and was subsequently fired. Unfortunately, he did a poor job of scope definition. 

Which of the following could happen if you don't correct this?

A. The project costs could increase, there might be rework, and schedule delays might result.
B. The project management plan's process for verification and acceptance of the deliverables 
    needs to be updated as a result of the poor scope definition.
C. The poor scope definition will adversely affect the creation of the work breakdown structure, 
    and costs will increase.
D. The stakeholders will require overtime from the project team to keep the project on schedule.

Answer: A

Explanation:
Option A might seem like a correct answer, but option D is more correct. There isn't enough information to determine whether stakeholders will require overtime. We do know that poor scope definition might lead to cost increases, rework, schedule delays, and poor morale.

Question 7.
You are a project manager working in a foreign country. You observe that some of your project team members are having a difficult time adjusting to the new culture. You provided them with training on cultural differences and the customs of this country before arriving, but they still seem uncomfortable and disoriented. 

Which of the following statements is true?

A. This condition is known as culture shock.
B. This is the result of jet lag and travel fatigue.
C. This is the result of working with teams of people from two different countries.
D. This condition is known as globalculturalism.

Answer: A

Explanation:
When people work in unfamiliar environments, culture shock can occur. Training and researching information about the country you'll be working in can help counteract this.

Question 8.
Which of the following is not true for a Responsibility Assignment Matrix (RAM):

A. Defines what project member is responsible for each activity
B. Defines responsibilities for each WBS component
C. Defines all people associated with each activity
D. Text description of roles, responsibilities, authorities

Answer: D

Explanation:
The Responsibility Assignment Matrix (RAM) details the different tasks for the people listed in the matrix chart.

Question 9.
The erection of foundation formwork before the placement of foundation concrete would be an example of a _____ dependency.

A. Soft logic
B. Subcontracted
C. Mandatory
D. Discretionary
E. External

Answer: C

Question 10.
You are the project manager of a project .You have just completed the Collect Requirements and Define Scope. 

What should you do next?

A. Control Scope
B. Create WBS
C. Value analysis
D. Verify Scope

Answer: B

Explanation:
Create the WBS is the process that follows Collect Requirements and Define Scope.


Google
 
Web www.certsbraindumps.com


Study Guides and Real Exam Questions For Oracle OCP, MCSE, MCSA, CCNA, CompTIA





              Privacy Policy                   Disclaimer                    Feedback                    Term & Conditions

www.helpline4IT.com

ITCertKeys.com

Copyright © 2004 CertsBraindumps.com Inc. All rights reserved.